What is a data center moratorium?

A data center moratorium is a temporary, legally binding pause on approving, permitting or building new data centers in a town, county or state. It buys a government time to study the effects on power, water, land and utility bills, and to write rules before more projects move forward.

In 2026, moratoriums went from rare to routine. New York became the first state to adopt one in July. Dozens of counties and cities have paused new projects, and Virginia lawmakers will debate statewide moratorium bills when the General Assembly meets in January 2027.

This guide covers how a moratorium works, how it differs from a ban, where moratoriums have passed, and what is on the table in Virginia.

How a Data Center Moratorium Works

Who can enact one:

A county board or city council can pass one through a zoning ordinance or resolution. A state legislature can pass one as a law. A governor can order one, as New York’s did. Utilities and grid operators sometimes pause new large hookups, which works much like a moratorium even when it isn’t called one.

What it usually pauses:

  • New applications for rezonings, special use permits and site plans

  • State permits, such as environmental or air permits

  • Sometimes new grid connections and power plants built to serve data centers

What it usually does not do:

  • Shut down data centers that are already running

  • Cancel approvals already granted. Most moratoriums freeze new applications rather than revoke old ones.

  • Stop projects that already hold permits and have spent heavily on construction (known as vested rights)

Size limits:

Many moratoriums cover only large facilities. New York’s executive order applies to data centers using 50 megawatts (MW) or more. New York’s legislative bill and the proposed federal bill set the line at 20 MW.

How long it lasts:

Most local moratoriums run from a few months to a year. Emergency ordinances can be as short as 60 days. Some proposals run longer: Maryland’s Montgomery County adopted 18 months, and Virginia’s SB 843 proposes three years.

The typical life cycle:

  1. Residents raise concerns about a wave of new proposals.

  2. The government adopts a pause with an end date.

  3. Staff or outside experts study grid, water, noise, land and cost impacts.

  4. Officials write new zoning rules or state standards.

  5. The pause ends, is extended, or is replaced by permanent rules.

Data Center Moratorium vs. Ban

A moratorium is temporary and comes with a plan to set rules. A ban is permanent or open-ended. Here is how a moratorium compares with the other tools governments use.

  • Moratorium: Pauses new approvals, permits or construction. Lasts months to a few years. Example: New York’s executive order, July 2026.

  • Ban: Prohibits data centers in some or all zones. Permanent or indefinite. Example: Monterey Park, California.

  • Pause on votes: Delays final decisions on pending applications for up to 12 months. Example: Loudoun County, Virginia (proposed in 2026).

  • Grid connection pause: A utility or grid operator stops new large hookups until it adds capacity. Examples: AEP Ohio (ended July 2025); Dublin, Ireland.

  • Tax-break moratorium: Stops new subsidies but not construction, for a set number of years. Example: Arizona, three years (2026).

  • Ending by-right zoning: Requires a public hearing for every project, permanently. Example: Prince William County, Virginia (September 2026).

Why Communities Want a Data Center Moratorium

  • Electric bills and grid strain. New York’s order noted that nearly 12,000 MW of data center demand was waiting in the state’s grid queue as of May 2026, more than 8,000 MW of it added in 2025 alone. The order also warned that projected demand doesn’t always arrive, which can leave ratepayers paying for infrastructure nobody uses.

  • Water. Large facilities can draw heavily on local water supplies for cooling, often in places already facing drought.

  • Noise and diesel fumes. Data center noise has been measured at 96 decibels, about as loud as a chainsaw. Loudoun County residents have filed waves of complaints about noise and generator exhaust.

  • Land and speculation. Proposed campuses tie up farmland and forest, and many proposals are speculative projects that may never be built.

  • Tax breaks. Virginia’s sales tax exemption for data centers costs more than $1.6 billion a year.

  • Outdated rules. Most zoning codes were written before 100-plus-megawatt facilities existed. A pause gives officials time to catch up.

  • Public opinion. National polling, including Gallup’s, finds that most Americans don’t want a data center built near their home.

Where Data Center Moratoriums Have Passed

Trackers count differently, but all of them show fast growth. In August 2026 the National League of Cities counted at least 76 local governments that had tried to adopt a moratorium or permanent ban, and most succeeded. Georgia Tech counted almost 40 in Georgia alone.

  • New York (state, executive order): Up to a one-year pause on state permits for data centers of 50 MW or more. July 14, 2026.

  • Montgomery County, MD: 18-month moratorium on new construction. July 2026.

  • Chesapeake, VA: Eight-month pause. July 2026.

  • Charlotte, NC: 150-day moratorium. June 2026.

  • Sunbury, OH: Moratorium through January 2027. April 2026.

  • Fulton County, IN: One-year moratorium. March 2026.

  • Aurora, IL: 180-day moratorium on data centers and warehouses. September 2025.

  • Prince George’s County, MD: Six-month moratorium. September 2025.

  • Fluvanna County, VA: Moratorium while zoning is rewritten. September 2025.

  • St. Charles, MO: One-year moratorium. August 2025.

Efforts that stalled: Maine’s legislature passed a statewide moratorium, but Gov. Janet Mills vetoed it. In Texas, Hood County dropped its proposal after a state senator threatened legal action. As of mid-2026, lawmakers in at least 14 states had tried to pass statewide moratoriums, and none had become law.

At the federal level: Sen. Bernie Sanders and Rep. Alexandria Ocasio-Cortez introduced the Artificial Intelligence Data Center Moratorium Act on March 25, 2026. It would halt construction or upgrades of data centers drawing 20 MW or more nationwide. It has not passed.

Outside the U.S.: Amsterdam paused new data center construction around 2020. Ireland restricted new data center grid connections around Dublin. Denmark introduced a grid connection pause in 2026.

Is There a Data Center Moratorium in Virginia?

Not statewide, at least not yet. Virginia is the world’s largest data center market, with more than a quarter of all operating capacity in the Americas. Pew Research counts nearly 400 operating data centers in Virginia and more than 280 planned. That makes the coming session one of the most important moratorium fights in the country.

Bills for the January 2027 General Assembly session:

  • SB 843 (Sen. Russet Perry, D-Loudoun, with Sen. Danica Roem, D-Prince William): a three-year statewide moratorium from July 1, 2027, to July 1, 2030. As drafted, it would bar localities from approving data center rezonings, special exceptions, special use permits and site plans. It would also bar state agencies from issuing data center permits and from authorizing power lines, grid connections or on-site generation for new data centers.

  • Sen. Glen Sturtevant (R-Chesterfield) has called for an immediate, indefinite moratorium and plans to file his own bill.

  • Sen. Roem is also filing a separate moratorium bill tied to the queue of data centers waiting for power from Dominion Energy.

  • HB 1515 (Del. Irene Shin), a temporary moratorium bill from 2026, was carried over to the 2027 session.

What Does Governor Spanberger Think About a Data Center Moratorium?

On Sept. 18, 2026, Gov. Abigail Spanberger signed Executive Order 22, her Data Center Accountability Framework. It bans nondisclosure agreements on new projects, ends by-right approvals and requires local approval for facilities over 25 MW. It does not include a moratorium and has widely been recognized by grassroots advocates as not going far enough. The governor has said a pause is a local choice, not a state one.

What localities are doing:

  • Loudoun County voted 7-1 on Sept. 15, 2026, to move toward pausing final votes on data center and substation applications for up to 12 months. The county attorney advised that an outright moratorium would not be legal. The formal resolution was pushed to the board’s Nov. 17 meeting.

  • Prince William County voted 8-0 on Sept. 22, 2026, to largely end by-right data center development.

  • Fluvanna County adopted a moratorium in September 2025. Chesapeake approved an eight-month pause in July 2026. Suffolk is pausing new applications while it rewrites its rules.

Why a statewide pause matters: Virginia follows the Dillon Rule, so counties have only the powers the state gives them. That’s why Loudoun’s lawyers questioned a full moratorium. Local pauses also stop at the county line, so developers can simply move next door. SemiAnalysis found that of roughly 20 gigawatts of planned capacity inside areas with local restrictions, only about 7.6% was actually delayed. A statewide pause tied to a real study closes those gaps.

Data Center Moratorium FAQs

Does a moratorium shut down existing data centers?
No. A moratorium pauses new approvals, permits or construction. Data centers already running keep operating.

How long does a data center moratorium last?
Most last six months to a year. Emergency versions can be 60 days, and some proposals run three years or more.

What is the difference between a moratorium and a ban?
A moratorium is temporary and usually tied to a study or new rules. A ban is permanent or open-ended.

Which state was first to pass a data center moratorium?
New York. Gov. Kathy Hochul signed an executive order on July 14, 2026, pausing state permits for data centers of 50 MW or more for up to a year.

Is there a federal data center moratorium?
No. The Artificial Intelligence Data Center Moratorium Act was introduced in March 2026 but has not passed.

Can a Virginia county pass a data center moratorium?
It’s legally contested. Under the Dillon Rule, Virginia localities have only the powers the state grants them. Fluvanna and Chesapeake have adopted pauses, but Loudoun’s attorney said a full moratorium would not be legal there. A state law would remove the doubt.

Will a moratorium lower my electric bill?
Not right away. It slows new demand while the state decides who pays for the power plants and transmission lines data centers require.

How can I support a data center moratorium in Virginia?
Sign our petition, contact your state senator and delegate before the January 2027 session, and speak at your county’s data center hearings.

Virginians Have Had Enough

Virginia has carried the data center boom longer and more heavily than any other state. A statewide moratorium would give Virginia time to study the combined impact on our water, grid, land and bills, and to weigh whether Virginia’s resources can handle the strain of additional data center construction. Add your name to the petition to stop new data centers in Virginia.